How to Set the Timer Controller of a Sand and Dust Test Chamber

Source:LINPIN Time:2025-05-06 Category:Industry News

How are the parameters of the sand and dust test chamber timer controller set? Here’s a guide: Today, we’ll share the detailed steps for operating the timer controller.

Before operating the timer controller of the sand and dust test chamber, ensure that the power is connected, as these operations must be performed with the power on. Initially, the controller display will show the main menu: Run, Function Block, Clear Program, etc.
sand and dust test chamber

Access the Function Block

Press the Up/Down Arrow keys to move the cursor to Function Block, then press OK (Confirm).
The screen will display “T1” (Test Time) in the lower right corner, with the cursor blinking on “T1”.
Set the Test Time (T1)

Press the Left/Right Arrow keys to move the blinking cursor to the time setting position.
Observe the time unit displayed in the upper left corner of the screen.
Press SEL, then use the Up/Down Arrow keys to adjust the desired time value.
Press OK to confirm, and the cursor will return to “T1”.
Set Blowing Dust Time (T2)

Press the Up Arrow and SEL keys simultaneously—the screen will display “T2” (Blowing Dust Time, recommended: 5 minutes).
Follow the same method as T1 to set the time.
Set Blowing Dust Stop Time (T3)

Press the Up Arrow—the screen will display “T3” (Stop Blowing Dust Time, recommended: 2 minutes).
Set it using the same method as T1.
Set Vibration and Power Times (T4-T7)

T4: Vibration Time (recommended: 0.5 seconds).
T5: Stop Vibration Time (recommended: 2 minutes).
T6: Power-On Time (set according to relevant standards).
T7: Power-Off Time (also set according to standards).
Complete Setup and Start the Test

After setting all 7 time parameters, press ESC (Exit) to return to the main menu.
Use the Up Arrow to move the cursor to “Run”, then press OK—”Run” will change to “Stop”, and the internal power will activate.
The temperature controller will display readings. Press ESC again to return to the control screen.
Begin the Test

Turn on the “Blowing Dust” and “Vibration” switches—the device will start working.
To begin the test, turn on the “Sample” switch.
That’s all for the operation steps of the sand and dust test chamber timer controller. By reading this guide, you should now have a clear understanding of the process.

News Recommendation
The entire testing process of a salt spray test chamber is relatively straightforward, and with technological advancements, the operation has become even simpler and more intelligent.
Thermal-Shock Chambers (TSCs) impose severe temperature ramps (−70 °C ↔ +200 °C within ≤5 min). Superimposed mechanical and thermal stresses exponentially raise failure rates.
High-low temperature test chambers are precision instruments that must be operated strictly by trained personnel following standard procedures and subjected to regular preventive maintenance. Any operational error or neglected upkeep can trigger a variety of faults, delaying test schedules. The equipment integrates refrigeration, heating, humidification, electrical control and other subsystems. Effective troubleshooting therefore requires a holistic “whole-machine mindset” to pinpoint and solve problems quickly.
Recently, Linpin Instrument efficiently completed a sma […]
Dust testing, codified in GB/T 2423.37 and IEC 60068-2-68, is now mandatory for proving the sealing integrity and reliability of military, automotive, photovoltaic and rail-transit products. Direct test outlays—consumables, energy, labour and depreciation—seldom exceed one to three per cent of the selling price, yet hidden expenses triggered by poor chamber selection—repeat tests, invalid data or after-sales downtime—can leap to eight to twelve per cent.
Product Recommendation
Telegram WhatsApp Facebook VK LinkedIn