How to Set the Timer Controller of a Sand and Dust Test Chamber

Source:LINPIN Time:2025-05-06 Category:Industry News

How are the parameters of the sand and dust test chamber timer controller set? Here’s a guide: Today, we’ll share the detailed steps for operating the timer controller.

Before operating the timer controller of the sand and dust test chamber, ensure that the power is connected, as these operations must be performed with the power on. Initially, the controller display will show the main menu: Run, Function Block, Clear Program, etc.
sand and dust test chamber

Access the Function Block

Press the Up/Down Arrow keys to move the cursor to Function Block, then press OK (Confirm).
The screen will display “T1” (Test Time) in the lower right corner, with the cursor blinking on “T1”.
Set the Test Time (T1)

Press the Left/Right Arrow keys to move the blinking cursor to the time setting position.
Observe the time unit displayed in the upper left corner of the screen.
Press SEL, then use the Up/Down Arrow keys to adjust the desired time value.
Press OK to confirm, and the cursor will return to “T1”.
Set Blowing Dust Time (T2)

Press the Up Arrow and SEL keys simultaneously—the screen will display “T2” (Blowing Dust Time, recommended: 5 minutes).
Follow the same method as T1 to set the time.
Set Blowing Dust Stop Time (T3)

Press the Up Arrow—the screen will display “T3” (Stop Blowing Dust Time, recommended: 2 minutes).
Set it using the same method as T1.
Set Vibration and Power Times (T4-T7)

T4: Vibration Time (recommended: 0.5 seconds).
T5: Stop Vibration Time (recommended: 2 minutes).
T6: Power-On Time (set according to relevant standards).
T7: Power-Off Time (also set according to standards).
Complete Setup and Start the Test

After setting all 7 time parameters, press ESC (Exit) to return to the main menu.
Use the Up Arrow to move the cursor to “Run”, then press OK—”Run” will change to “Stop”, and the internal power will activate.
The temperature controller will display readings. Press ESC again to return to the control screen.
Begin the Test

Turn on the “Blowing Dust” and “Vibration” switches—the device will start working.
To begin the test, turn on the “Sample” switch.
That’s all for the operation steps of the sand and dust test chamber timer controller. By reading this guide, you should now have a clear understanding of the process.

News Recommendation
This equipment provides an accelerated testing method to evaluate the corrosive effects of sulfur dioxide-polluted atmospheres on contact points and connectors, particularly suitable for comparative testing.
An aging test chamber does not refer to a single device but encompasses various testing methods, including xenon lamp aging tests, UV aging tests, high-temperature aging tests, air-exchange aging tests, and salt spray corrosion aging tests.
Conducting salt spray tests in natural environments through exposure is not only time-consuming but also yields results that are often inconsistent and difficult to control.
Rain test chambers are now widely used across various industries. When operating this equipment, staff should be familiar with essential knowledge, such as the necessary pre-use inspections. Let’s go through them today.
Although both thermal-shock and steady-state temperature/humidity tests fall under the umbrella of “weathering verification”, they differ fundamentally in physical modelling, control logic and safety strategy.